Building Quality and Safety Certificate in Dubai
Under Dubai Law No. 3 of 2026, every building needs a Building Quality and Safety Certificate once 20 years have passed since its completion certificate. We inspect the building, write the technical report, supervise the repairs and apply for the certificate for owners and owners associations.
Your building
Enter the year to see when the certificate applies, how long it will be valid and what to do next.
Based on Law No. 3 of 2026, Articles 9, 10 and 13, and Dubai Municipality’s circular. Where no completion certificate was issued, the authority sets the start date.
How to get a Building Quality and Safety Certificate
Five parties pass the file between them against legal deadlines. The steps follow Article 8 of the law and Dubai Municipality’s circular. Pick your role to see only your part.
Owner
or management entity
Receives the notice and its deadline
Appoints an engineering firm classed for the building’s height
Gives access to common areas, roof and plant rooms
Agrees the repair plan and timeframe
Hires the contractor
Renews every 10 or 5 years
Optimal
your consultant
Confirms our classification fits and opens the application on the Dubai Building platform
Inspects against the DM checklist; an accredited lab runs the tests
Files the report: defects, repair methods, materials and timeframe
Supervises the work on site
Confirms every defect is closed and applies for the certificate
Dubai Municipality
or the zone’s authority
Sends notices in phases, oldest multi-storey buildings first
Gives initial approval to start the assessment
Reviews the report and issues the remediation permit
Inspects the building and issues the certificate
Contractor
Dubai-licensed
Repairs within the approved timeframe
Occupants
tenants
Allow access to their units when asked
Vacate if the approved report requires it
Up to 6 months from initial approval to the report (extendable to 2 years)Art. 8(2)
3 months for occupants to vacate, if requiredArt. 12(b)(3)
Renew in the last 90 daysDM
- 1
Step 1: Notice
- Owner
- Receives the notice and its deadline
- Dubai Municipality
- Sends notices in phases, oldest multi-storey buildings first
- 2
Step 2: Appointment
- Owner
- Appoints an engineering firm classed for the building’s height
- Optimal
- Confirms our classification fits and opens the application on the Dubai Building platform
- Dubai Municipality
- Gives initial approval to start the assessment
Up to 6 months from initial approval to the report (extendable to 2 years) Art. 8(2)
- 3
Step 3: Inspection
- Owner
- Gives access to common areas, roof and plant rooms
- Optimal
- Inspects against the DM checklist; an accredited lab runs the tests
- Occupants
- Allow access to their units when asked
- 4
Step 4: Technical report
- Owner
- Agrees the repair plan and timeframe
- Optimal
- Files the report: defects, repair methods, materials and timeframe
- Dubai Municipality
- Reviews the report and issues the remediation permit
3 months for occupants to vacate, if required Art. 12(b)(3)
- 5
Step 5: Repairs
- Owner
- Hires the contractor
- Optimal
- Supervises the work on site
- Contractor
- Repairs within the approved timeframe
- Occupants
- Vacate if the approved report requires it
- 6
Step 6: Certificate
- Owner
- Renews every 10 or 5 years
- Optimal
- Confirms every defect is closed and applies for the certificate
- Dubai Municipality
- Inspects the building and issues the certificate
Renew in the last 90 days DM
No defects found? The consultant applies for the certificate straight after the inspection, and the report and repair steps fall away.
What does the inspection check?
The technical report has to address every item on Dubai Municipality’s checklist, and in particular these six, set out in Article 7(d) of the law.
Dubai Municipality reviews and updates the checklist and publishes changes on the digital platform (Article 7(e)), so we work from the current version on each building.
Validity, deadlines and fines
The numbers that set your timetable, as written in the law. Where news reports and other guides disagree, this table follows the law and Dubai Municipality’s own announcement.
| Rule | What the law sets | Source |
|---|---|---|
| Validity, building under 40 years | 10 years, renewableArt. 13 | Art. 13 |
| Validity, building 40 years or older | 5 years, renewableArt. 13 | Art. 13 |
| Renewal window | The last 90 days before expiryDM, Oct 2026 | DM, Oct 2026 |
| Technical report | Within 6 months of initial approval, extendable up to 2 years if there is no riskArt. 8(2) | Art. 8(2) |
| Occupants vacate, if repairs require it | Within 3 months of the report’s approval, with priority to return at the same rentArts. 12, 15 | Arts. 12, 15 |
| Fines | AED 100 to 1,000,000; doubled for a repeat within 2 years, up to AED 2,000,000Art. 16 | Art. 16 |
| Other measures | Suspension of building permits and of lease attestation for the buildingArt. 16(c) | Art. 16(c) |
| Demolition instead | Exemption with up to 1 year to demolish and a refundable AED 50,000 depositArt. 14 | Art. 14 |
Law No. 3 of 2026 was issued on 27 February 2026. The Arabic text prevails. Fees and the list of violations are set by Executive Council resolution.
What to send us
With these we can confirm the scope, the classification needed for your building’s height and a fee proposal, usually from one message.
- 1The Dubai Municipality notice, if you have one
- 2The completion certificate
- 3The title deed or affection plan
- 4As-built drawings and maintenance records, if available
Questions owners ask
Who can carry out the assessment?
An engineering firm registered with Dubai Municipality whose classification matches the building’s height (Article 7). The firm must write the report itself, and any lab tests must be done by a Dubai-licensed laboratory accredited by the Emirates International Accreditation Centre.
How much does the certificate cost?
There are three parts: the authority’s fee, set by Executive Council resolution; the consultant’s fee, which depends on the building’s height, size and the tests needed; and the cost of any repairs. We quote our fee after seeing the notice and the completion certificate.
Are any buildings exempt?
The law applies across Dubai, including free zones and special development zones such as DIFC. Only the Chairman of the Executive Council can exempt a specific building. An owner who chooses to demolish, or a building the authority orders demolished, does not need the certificate (Articles 3 and 14).
What if the inspection finds no defects?
The consultant applies for the certificate straight after the inspection, through the e-service on the Dubai Building platform. Dubai Municipality then inspects the building and issues the certificate.
Is this the same as a building completion certificate?
No. The completion certificate is issued once, when construction finishes. The Quality and Safety Certificate is issued 20 years later, after an inspection of the existing building, and has to be renewed every 10 or 5 years.
Sources
- Law No. 3 of 2026 Concerning the Quality and Safety of Buildings in the Emirate of Dubai (English)
- Law No. 3 of 2026 (Arabic text, which prevails)
- Dubai Municipality (guide, laws and circulars under Planning and Building)
- Al Bayan: Dubai Municipality sets the validity rules for the Quality and Safety Certificate (October 2026)
- Emirates 24|7: 10-year and 5-year validity for Building Quality and Safety Certificates (9 October 2026)
Last reviewed 2026-11-25